The condition of the architectural members of the Parthenon is due to a combination of historical events, the most important of which are considered to be the fire of 287 B.C., vandalism and the explosion of 1687. In more recent historical times, unsuccessful interventions of conservation and restoration, extensive atmospheric pollution, mainly from 1950 on, have deteriorated the monument's condition. The state of preservation of most of the monument's architectural members is characterized by various sorts of damage, disintegration and flaking, thermal expansion and sulphation, biodeterioration, fractures, cracks and delaminations, extensive pointing with Meyer cement. The first pilot project of systematic interventions carried out in 1988 and was focussed on the second column from the north in the east end of the temple. Following that, the conservation programme of the monument was planned and developed in coordination with the broader restoration programme.
The interventions are focussed on the following:
East Side: the systematic conservation on the members of the entablature and on the columns is completed.
Opisthonaos: preventive conservation work was carried out while the entablature was being dismantled. This was followed by systematic conservation of the columns and the dismantled members. This work was finished in 2005.
West Frieze: Preventive conservation work was accomplished during the dismantling. This was followed by systematic conservation, and cleaning of the frieze blocks. This work was completed in 2005.
Pronaos: Preventive interventions were carried out during the dismantling and resetting of the columns and architrave blocks. In addition, systematic conservation was conducted on the sixth from the north column. After the work was completed, an artificial patina was applied on the supplements of new marble.
North Side: Preventive interventions were carried out on the entablature and the columns during their dismantling. Likewise members of the entablature and the seatings of the dismantled drums are being systematically conserved.
North Metopes: Preventive conservation interventions are being carried out.


Interventions Completed
Restoration of the east side of the monument, which had suffered very serious damage because of the earthquake of 1981, was carried out between 1984 and 1991. The proposal, based on the study by M. Korres, was to dismantle the corners of the pediment and the corresponding entablature. In the course of the work, however, previously invisible breaks in the architectural members were discovered, which led to the extension of the works to include the entire pediment together with the horizontal cornice, the Doric frieze and the capital and uppermost drum of the 7th from the north column. The intervention was extended also to include the first metopes of the north side and the underlying cornice. Removal of the architectural members was followed by their structural restoration and they were then reset in their original positions. It was decided that it was necessary to replace the original metopes with copies in artificial stone.

In February 1992 work began on the restoration of the 5th column from the east in the south colonnade. The column had been damaged during the explosion of 1687, with the result that it had shifted and was inclined toward the south. Since the problem lay in the first drum, the column from the second drum up had to be removed as a whole, so that the continuity of the intermediate drums would be undisturbed. The intervention was carried out using an improvised mechanism for clasping and transporting that was designed by M. Korres and K. Zambas. The column was moved all in one piece and placed temporarily in the interior of the temple, while the first drum was being restored. The intervention was completed in July 1993.

Restoration of the pronaos of the Parthenon was carried out between the years 1995 and 2004, on the basis of the approved study of M. Korres. The proposal was for partial restoration of the first three columns from the north and the complete restoration of the fourth and fifth columns. Structural restoration was carried out on the members of the second, third, fourth and fifth columns from the north and on the preserved architrave blocks of the 4th and 5th intercolumniations. The sixth from the north column was dismantled down to the level of the second drum and was completely reassembled after its members were structurally restored. Relevant studies were carried out by the civil engineer M. Mentzini. Structural restoration were carried out by the civil engineers K. Zamba and M. Mentzini. All the new supplements were given an artificial patina so as to lessen the contrast between ancient and new marble. It remains to carve the fluting of the new marble pieces in the columns and to reset the architrave between the porch and the SE anta.

The programme for restoring the opisthonaos began in 1992, on the basis of the relevant study by P. Kouphopoulos, who was in addition the technical advisor for the work. The programme was implemented in two stages and completed in 2004. While the work proceeded, supplementary implementation studies were made by the architect P. Christodoulopoulou and studies for the structural restoration of the architectural members were made by the civil engineer E. Toumbakari. The first phase of the programme comprised the dismantling of the roof beams of the colonnade, the crown blocks of the west porch, and the west frieze blocks, which were taken to the Acropolis Museum in 1993. The second phase of the programme began in 2001 with the dismantling of the remaining members of the entablature of the west porch, a number of column capitals and top column drums. After all the members had been restored and some had been reassembled from ancient fragments, they were reset in the summer of 2004. The blocks of the west frieze that had been removed from the monument were replaced by copies cast in artificial stone. Consolidation of those columns that had never been dismantled in the past was carried out in situ, with special injections, in order to retain their authentic structure intact. This was done on the basis of the study by the civil engineer A. Miltiadou.

The restoration of the north colonnade of the temple began in October 2001. The approved study (initial study by K. Zambas, definitive study and implementation study by L. Lambrinou and R. Christodoulopoulou) stipulated the dismantling of eight columns (from the 4th to the 11th from the east) and the corresponding parts of the entablature above, the replacement of the concrete supplements of the previous intervention with supplements of new marble, the resetting in the monument of all identifiable ancient pieces, the replacement of existing clamps and dowels with corresponding ones of titanium and the anastelosis of the architectural members in their original positions so as to correct the earlier misplacements and transpositions. The structural restoration of the architectural members is being carried out on the basis of the relevant studies by the civil engineer M. Mentzini, and also by the engineers Ch. Kyparissi, E.E. Toumbakari and A. Vrouva. Much of this work has now been finished and the project is continuing at a good pace. In 2007 the programme was expanded to include the dismantling of the 7 ancient metopes that were still in situ and the conservation - restoration of the members of the west part of the entablature of the north peristyle (study by P. Chistodoulopoulou).

Completion of the intervention gave to the monument both structural strength and aesthetic wholeness, since the north side and the west side of the Parthenon together provide one of the most complete views of the temple, both for the visitor to the sacred rock and from most points of the city.

Interventions in process
The new restoration project, which is funded by the NSRF, includes an extensive program of interventions on the Parthenon.
The most important intervention relates to the west side of the monument, which was restored by N. Balanos during earlier restoration activities (1898-1902). The intervention aims:
a) to address the serious structural problems and deformations of this part of the monument, due to damages of the past, the oversights of previous restorations and the effect of earthquakes
b) to facilitate the structural restoration of most architectural parts and their supplement with new marble on several occasions, for reasons of structural adequacy.
The new study for the intervention was prepared by the architects B. Eleftheriou and V. Manidaki alongside the Engineer A. Vrouva.
In the restoration programme for 2011-2015 the intervention on the two corners of the west side of the monument has been included. Since 2011, a total of 111 architectural blocks have been dismantled. These will be reset on the monument after the completion of their structural reconstruction. During the same time, from the two corners of the monument, a total of seven metopes were dismantled and transported to the Acropolis Museum for their display and
protection. Accurate copies in artificial stone have already been manufactured and will be placed on the monument as their replacement. Surface conservation is being carried out on all blocks that have been dismantled and on all blocks still in situ on the building. After structural restoration, the dismantled architectural members will be reset in their original positions on the monument.  In order to detect the extent of shifting that may have occurred in the corner columns and especially in the fourth column of the west side during the process of dismantling and resetting, a monitoring system has been installed with optical fibre sensors.
Together with the works on the west side, restoration interventions are also under way at the orthostate and the first section of the cella’s north wall. The current programme relates to the restoration and resetting in their original positions of 15 ancient blocks from the exterior course of the orthostate. The structural restoration of most of the blocks has been completed and their resetting on the monument has been initiated. From the internal row of the orthostate, only one ancient block has been identified. Further blocks will be made of new marble and placed in positions that lack original material, so as to support the overlying sections of the wall. The remaining parts of the north and south walls will be restored in successive programmes. The restoration of the side walls of the cella is based on the intervention studies of N. Toganidis and K. Paraschi for the south wall and
N. Toganidis and K. Matalas for the north wall. The implementation of this program will contribute to the recovery of the structure of the walls of the cella and the further enhancement of the architecture of the monument.
Current works on the Parthenon also include the completion of the carving of the flutes in the new marble additions of six columns of the north colonnade (4th – 9th columns from the east).  This is the final processing of the surface of the drums made of new marble and requires highly skilled craftsmanship. Three of the SE columns have already been completed. Further surface processing activities covered by the current NSRF relate to the carving of the flutes in the additions of the two northernmost columns of the five restored columns of the Pronaos (East Porch).
Finally, due to begin are the reconstruction works of the lintel of the door of the west wall of the cella that had been restored by N. Balanos. In this phase, the two internal beams, parts of which are preserved, will be restored and complemented with new marble. In a successive phase, blocks of the upper part of the west wall, the westernmost lintel’s block still in situ and blocks of the upper parts of the doorway will be dismantled. 